About 5 minutesSungrow blackout and manual changeover
Use only the labelled customer changeover or automatic backup arrangement supplied with your Sungrow installation.
Need the Sungrow monitoring app? Open the app articleBefore you start
Confirm the outage is real, check battery SOC in iSolarCloud and locate any clearly labelled GRID / BACKUP changeover switch.
- 01Turn off high-load appliances such as ovens, air conditioners, pumps, kettles and electric hot water before using backup power.
- 02If your Esena handover says the changeover is customer-operated, follow the label exactly. Move from GRID / NORMAL to BACKUP / INVERTER only as shown—never force it or open the switchboard.
- 03If your system has automatic backup, do not switch off the main supply yourself. Wait for the labelled backup circuits to transfer.
- 04Use essential appliances only. Only circuits connected to the backup output will operate and the battery has limited capacity.
- 05Check iSolarCloud for battery SOC, backup status and overload warnings. Do not change inverter settings or repeatedly reset a breaker.
- 06When grid power returns and is stable, follow the handover label to return to GRID / NORMAL. If the label is missing, unclear or backup does not start, call Esena on 1300 239 296.